Project acceptance

How do you define automation acceptance?

13 November 2026
Robot and handling tooling in a framed industrial work cell

SanSong technical guide · · Procurement planning guide

Define acceptance before equipment is built. Identify the supply boundary, representative products, evaluation conditions and responsibility for each interface. Separate checks of the supplied equipment from outcomes that depend on the surrounding line, then document the evidence needed for handover.

This buying guide helps prepare a technical discussion. The final equipment configuration and commercial scope are confirmed for each project.

Identify the supply boundary

List the machines, fixtures, controls and services included in the project. Identify upstream and downstream equipment outside that boundary.

Assign utilities, foundations, signal connections and installation work. A shared interface list reduces ambiguity during commissioning.

A clear application brief connects the product, the equipment and the acceptance criteria.

Choose representative conditions

Specify the parts, materials and product variants that will be available for evaluation. Record how results will be captured.

  • List the equipment, tooling and services included in the supply.
  • Identify equipment and outcomes outside that supply boundary.
  • Assign an owner to each control, utility and installation interface.
  • Select representative parts, materials and product variants.

If samples or conditions differ from the production requirement, document the limitation and any further checks needed.

Separate checks from assumptions

For each acceptance criterion, state the method, operating conditions, responsible party and required evidence.

Describe activities, operator involvement and dependencies rather than relying on an undefined phrase such as production ready.

Record handover and open items

Agree drawings, operating information and training topics required at handover. Keep a dated open-item list with owners. Record changes to product scope, interfaces or evaluation conditions so both teams use the same project definition.

Review the preparation checklist

Use the checklist to identify missing inputs, then assign an owner and a review date to each open question.

  • Define the method and operating conditions for each check.
  • Record who witnesses, approves and retains the evidence.
  • Agree handover documents, operating guidance and training topics.
  • Maintain a dated open-item list and a change-review process.

Keep approved requirements and open decisions separate. Review revisions with the people responsible for operation, maintenance and acceptance.

Confirm scope and responsibilities

Ask the relevant business team to confirm the proposed configuration, supplied items, exclusions and next evaluation step in writing.

Start your project discussion

Prepare supply boundary and an owner for each interface. Explore the related equipment or request an engineering quotation.

Business-scope source: SanSong published product documentation (Liuzhou Sansong Automation Technology Co., Ltd.). The preparation advice above is editorial guidance. Final configuration, performance, scope and acceptance criteria are confirmed in the project quotation.

Continue exploring

More questions before the next project

Ready to automate your workflow?

Talk to our experts and discover the right solution for your production.